The approval of the third stage of the
Plan for Tourist Excellence in Oviedo
will allow the beginning of the third
stage where the integral restoration
of the cover will be undertaken,
the restoration of the basements
due to be used as practice room and
the replacement of the dress circle
seats.
MASTER
PLAN
|
2.154.878 € |
1st Stage:
Electricity and IPC.
Beginning: September 2004.
End : January 2005 .
|
622.566 € |
2nd Stage:
Dressing rooms and stage. On tender.
Beginning expected in: February-March 2005
End expected in: July-August 2005
|
541.098 € |
3rd Stage:
Façade, Basement,
Cover and General area.
Pending tender and detailed dossier.
They are peripheral works and will not interfere with the general activity
|
(pending
approval) |
|